Projects

G+2 LABOUR ACCOMMODATION BUILDING – 4 BUILDINGS

  • Client: Arenco Real Estate
  • Consultant: ARENCO
  • Main Contractor: Robust Contracting

Scope of Work: MEP Works

Location: Dubai Investments Park, Dubai

Client: M/S Arenco Real Estate

Consultant: M/S ARENCO

Contractor: Robust Contracting

Status: Completed

 

Project Profile:

This project involved a district cooling system In addition to being a comprehensive MEP contract.

 

Scope of Work: Supply, Engineering, Installation, Testing, Commissioning, and Maintenance.

 

AIR-CONDITIONING AND VENTILATION SYSTEM

  • 8 Nos. heat exchangers.
  • 12 Nos. pumping system (secondary pumps).
  • 16 Nos. FAHU and 56 Nos. AHU.
  • 8 Nos. central exhaust fans.
  • Connection to district cooling system.

 

PLUMBING AND WATER SUPPLY

  • RCC U/G water tank of 160 m3 capacity.
  • 8 Nos. Transfer and Booster Pump Sets.
  • 4 Nos. GRP water tank 60 m3 capacity each.
  • Installation of all sanitary wares and fittings.
  • Plumbing and domestic water work.

 

FIRE-FIGHTING WORK

  • UL- listed fire fighting pump sets.
  • Wet and Dry risers, with sprinklers and hose reel cabinets.
  • Fire alarm system.

 

ELECTRICAL WORK

  • Power system with a total of 1.8 MW total connected load.
  • 9 Nos. MDB, 12 Nos. SMDB and 24 Nos. FDB.
  • All related power and lighting cabling.
  • ELV Systems: SMATV, CCTV, and Public Address systems.